Another good turnout with 22 crew members showing up to continue work on the Pine Mountain Trail. The major achievement for the day was opening a new keyhole between the trail and fire road.
Pine Mountain - Upper Section and Sequoia Trail
The April 4th effort was another two crew day as the push to complete work on Sequoia Trail before it opens to the public is in its final stages and park staff asked if we could double back and do QC work on the stretch between Jay Camp and Wastahi that had become a little shaggy with regrowth in recent months. With the timeline constraint this work was our priority for the day, but we also wanted to continue the current work on Pine Mtn Trail. Fortunately, with a good size crew of 22 we were able to split in half to accomplish both goals.
Pine Mountain - Upper Section and Sequoia Trail
The Trail Crew's March 21st workday was a throwback to the pre-2020 fire days when we would split into two (and sometime three) crews when there were multiple trails that needed attention and we wanted to cover as much ground as possible. But since the fires we have worked one trail at a time as we focus on helping reopen new sections of the park to visitors.
Pine Mountain - Upper Section
The Trail Crew's March 7th workday was a surprise early spring like day after the previous workday in late February was almost washed out by six inches of rain in the days leading up to it. Although nice not to be concerned about rain, the first warm day since last fall took some getting used to as well.
Pine Mountain - Middle Section
The Trail Crew entered its Feb. 21st workday with one goal in mind, but several potential challenges were standing in the way. Since mid-November we had become bogged down with final detail work in the section of trail below Pine Mtn Fire Rd. The slow progress was partly due to the Thanksgiving and end of year Holidays, but regardless we really wanted to complete the work and move on to the next section of trail.
Pine Mountain - Middle Section
Pine Mountain - Middle Section
Pine Mountain - Middle Section
The first workday of the new year was our first in a month and only the second since mid-November due to end of year holidays, so we hoped it would be a chance to catch up on things. After all there had been several weeks of wind and rain storms over the break that may have created new issues along with our standard post fire trail clearing work, so potentially a busy day.
Pine Mountain - Middle Section
Pine Mountain - Middle Section
The Trail Crew has been making good progress on Pine Mountain Trail and as the end of the year approaches we were hoping to punch through to the fire road crossing before the holidays settle in. There was another record tying turnout of 29 so we were able to reach the fire road on the Nov. 15th workday!









