Pine Mountain - Upper Section

After two consecutive mid-to-upper 80's workdays day, the Trail Crew finally encountered fall weather on it's Oct. 31st workday and was able to put in a full day.  Whether it was the milder weather or most of the crew returned from summer travels, we had a turnout of 27 and were able to spread out along the trail. 

Most of the crew resumed work where we left off last time as we continued moving debris from the trail edge to a previously established off trail stash site. Meanwhile others moved further along the trail to identify and open the next off trail hiding location. 

And a third crew disappeared well up the trail to continue removing trip hazard stubs from the trail corridor that were left from the initial clearing work back in September.  It turned out to be a successful day in near perfect trail working conditions (map: yellow work area and red stash area). 

The crew put in 198 hours and thanks to Fremont Bainbridge, Rory Brooks, Karen Cheeniyil, Santhosh Cheeniyil, Dan Chen, Peter Gelblum, Drew Granzella, Mimi Guiney, Tommy Ha, Joe Jerkins, Janie Leifhelm, Bill Lock, Jack Marshall, Cindy Marten, Eric Marten, John Martin, Mike Peasland, Chris Rempis, Angelina Thomas,  Brian Washburn, Bruce Washburn, Jill Zeng, Daniel Zichuhr, and newcomers Mark Gerber, David Lindley, Roger Lindley and Mac Murrett, for the support. 


Big Basin has a number of iconic trees like the 'Mother of the Forest' and 'Father of the Forest' on the Redwood Loop Trail and for past year the Trail Crew  had its own landmark tree on Pine Mtn Trail below the fire road: ‘Cannonball Tree' or 'Tree of Death'.

Much of the tree's heartwood was burned out during the fire and it didn't appear there was much holding it upright. We were surprised that it was still standing after the 2025-26 winter.  Two of the BBVTC crew were still out on the trail at the end of the Oct. 17th workday when they came across two District trail crew members who were following up on hazardous tree reports.  

After helping them locate the tree, the decision was made to remove it immediately due to its unstable condition and winter rains arriving in the next month or so.   After being dropped it became clear the decay at the base of the tree would have definitely made it more dangerous in a fairly short time. But perhaps the most surprising aspect was even with all the fire damage and decay, the tree still came down in one piece!


by Mike and Jeff

photos and video by Bill, Bruce, Daniel, Mike, Mimi, John M., and Tommy

Pine Mountain - Upper Section

Pine Mountain - Upper Section

The Trail Crew's Oct. 17th workday picked up where the previous one left off, which also meant it was another warm day on the upper third of Pine Mtn Trail. It was also the first time the BBVTC, District, and CCC crews, have all worked the same section of trail at the same time, so it required extra focus on planning coordination to ensure everything went smoothly. 

Pine Mountain - Upper Section

Pine Mountain - Upper Section

Five days before the Trail Crew's Oct. 3 workday the weather forecast was calling for temperatures in the mid-90's for the upcoming weekend and 48 hours beforehand an official heat advisory was posted for the entire Bay Area.  And working on the side of Pine Mountain near the 2,100 foot Buzzards Roost summit seemed to guarantee it would be hot.

Pine Mountain - Upper Section

Pine Mountain - Upper Section

With a CCC crew set to arrive in four days to begin follow-up work on Pine Mtn Trail, the sole focus of the workday was to punch through a rough cut trail between the two crews working toward each other along the final section of unworked trail.  The sprint to the finish began the previous workday and with less than one-half mile of trail remaining uncleared the goal seemed within reach.

Pine Mountain - Upper Section

Pine Mountain - Upper Section

The usual methodical approach that the crew have been using would need to give way to a sprint with the focus on completing a rough cut trail. Everything else that needed to be done could wait until the CCC arrives and we have help with the remainder of the work. So with a crew of 16 for the Sept. 12 workday, we decided to split into two groups with one continuing uphill work from where we left off the previous workday while the second crew drove the fire road to Buzzards Roost and began clearing the trail in the downhill direction.

Sequoia Trail, North Section and STS, Sequoia to Gazos

Sequoia Trail, North Section and STS, Sequoia to Gazos

With many Trail Crew regulars away on summer travels, we decided to make the August 22nd workday a return to our roots by doing maintenance on an open trail.  Some on the Crew have done personal time hikes in the past couple of months and reported that a section of Skyline-to-Sea Trail (STS) was becoming overgrown while park staff said there were visitor reports of several small-medium size trees down on Sequoia Trail below 236.  

Pine Mountain - Upper Section

Pine Mountain - Upper Section

The objective of the work is to clear vegetation from trail edges so it doesn't impact the trail corridor itself, but it can sometimes be tedious work. Since the 2020 fires we've tried to stay current with brushing as we worked on clearing the trail itself. Letting trail clearing get too far ahead of brushing only meant we would have multiple days of brushing to catch up on at some point.