Pine Mountain - Upper Section

Pine Mountain - Upper Section

With a CCC crew set to arrive in four days to begin follow-up work on Pine Mtn Trail, the sole focus of the workday was to punch through a rough cut trail between the two crews working toward each other along the final section of unworked trail.  The sprint to the finish began the previous workday and with less than one-half mile of trail remaining uncleared the goal seemed within reach.

Pine Mountain - Upper Section

Pine Mountain - Upper Section

The usual methodical approach that the crew have been using would need to give way to a sprint with the focus on completing a rough cut trail. Everything else that needed to be done could wait until the CCC arrives and we have help with the remainder of the work. So with a crew of 16 for the Sept. 12 workday, we decided to split into two groups with one continuing uphill work from where we left off the previous workday while the second crew drove the fire road to Buzzards Roost and began clearing the trail in the downhill direction.

Sequoia Trail, North Section and STS, Sequoia to Gazos

Sequoia Trail, North Section and STS, Sequoia to Gazos

With many Trail Crew regulars away on summer travels, we decided to make the August 22nd workday a return to our roots by doing maintenance on an open trail.  Some on the Crew have done personal time hikes in the past couple of months and reported that a section of Skyline-to-Sea Trail (STS) was becoming overgrown while park staff said there were visitor reports of several small-medium size trees down on Sequoia Trail below 236.  

Pine Mountain - Upper Section

Pine Mountain - Upper Section

The objective of the work is to clear vegetation from trail edges so it doesn't impact the trail corridor itself, but it can sometimes be tedious work. Since the 2020 fires we've tried to stay current with brushing as we worked on clearing the trail itself. Letting trail clearing get too far ahead of brushing only meant we would have multiple days of brushing to catch up on at some point.

Pine Mountain - Upper Section

Pine Mountain - Upper Section

The work wasn't the biggest obstacle for the June 13th workday it was the warm temperatures and gnats that tested the Trail Crew's dedication. Despite temperatures in the upper 90's two days beforehand, 21 crew members still said they planned to be there. After months of work the Sequoia Trail is now open.